Request for Bids, Proposals, & Results

Bid Packages/ Request for Proposals

Prequalification for SR 105 Project

Status: Closed
Close Date:

Power Pole Inspection, Testing and Treatment Contract

Status: Closed
Close Date:

Purchase of Three (3) VFI 15 KV Underground Distribution Switchgears with Option – Bid No. 1114-2023

Status: Closed
Close Date:

Purchase of Electrical Meters (RE-BID) – Bid No. 2023-1157

Status: Closed
Close Date:

Purchase of a Steel Pole Structure and 115KV Three-Way Switch – Bid No. 2023-1145

Status: Closed
Close Date:

Unit Priced Contract for Routine and Emergency Trenching, Backfilling, Clearing, Hauling, Road Construction, Core Drilling, Excavation, Concrete/Asphalt Patching, and General Use of Equipment – Contract Term: Maximum of Three (3) Years Beginning May 15, 2023 for a Total Not to Exceed Amount of $349,000.00

Status: Closed
Close Date:

Purchase of Electrical Meters

Status: Closed
Close Date:

Purchase of Transmission and Distribution Poles

Status: Closed
Close Date:

Track Loader

Status: Closed
Close Date:

Janitorial Service

Status: Closed
Close Date:

Competitive Bid Results

Furnish & Supply 288 Meters. Bid Opening Held 7/8/2019 @ 1:00 p.m.

Bidder, Amount, & Lead Time

Anixter – $212.40 each – 17 - 19 weeks

Anixter alternate bid – $210.10 each – 17 - 19 weeks

General Pacific – $288.51 each – 16 - 20 weeks

Carlson Sales – $242.20 each – 16 weeks

Contract Awarded To

Anixter on July 23, 2019

Furnish & Supply 1 New Hydraulic Excavator. Bid Opening Held 4/4/2019 @ 11:00 a.m.

Bidders & Amounts

Cascade Trader – $261,000.00

(Cascade Trader bid an optional twin automated greasing system $7,740.00 = $268,740.00 with the option, if accepted by the district)

Modern Machinery – 268,504.00

Pape Machinery – $254,000.00

Contract Awarded To

Pape Machinery during the District's special commission meeting on Monday, April 22, 2019 at 4:30 p.m.

SR 105 Design/Build Project. Bid Opening Held 3/7/2019 @ 11:00 a.m.

Contractors & Price

Michels Power – No Bid

Wilson Construction – No Bid

Titan – Total (both construction and design without tax):  $1,897,699.00

DJ's Electrical – Total (both construction and design without tax):  $2,302,850.00

Burns & McDonnell – Late (arrived at 11:20 a.m. via FedEx)

Bids were rejected on Tuesday, April 30, 2019; The specifications are being revised and this project will be re-bid at a later date

Please contact Tiffanee Parson in the District's legal department at (360) 538-6384 to receive a new bid package once this project is re-bid.

Small Works Roster and Vendor List Contract Award Results

2023 Vendor Roster Awards
Vendor Description of Work Contract Amount PO # Date Contract Awarded
Stella-Jones Corporation Poles $26,794.50 230285 January 23, 2023
Stella-Jones Corporation Poles $69,665.70 230284 January 23, 2023
Stella-Jones Corporation Poles $102,671.10 230317 February 9, 2023
Stella-Jones Corporation Poles $54,147.60 230365 March 8, 2023
Power & Telephone Supply Fiber Optic Cable - 144 Ct. $72,800 230391 March 22, 2023
Elliott Industries Inc Switching Enclosures $91,852 230414 April 12, 2023
General Pacific Inc Fiber Optic Cable - 96 Ct. $44,700 230415 April 12, 2023
RJB Wholesale Inc. Conduit 3" $38,544 230555 July 14, 2023
NOJA Power LLC Reclosures $58,480 230582 July 27, 2023
McKaig Evergreen Inc. Switchgear Enclosure $76,471 230661 September 13, 2023
Anixter Inc 1100 Aluminum Primary Cable $72,920 230707 October 17, 2023
Anixter Inc 750 Copper Wire $47,730 230707 October 17, 2023
Anixter Inc Meters 2S From 320 $66,134 230720 October 19, 2023
Stuart C Irby Co. Conduit 3" $32,736 230752 December 12, 2023
2022 Vendor Roster Awards
Vendor Description of Work Contract Amount PO # Date Contract Awarded
Border States Electrical Triplex Wire #4 Non Pariel $57,855.00 220262 January 11, 2022
Stuart C Irby Co. 115KV Insulators $45,684.00 220268 January 13, 2022
General Pacific Inc. Cutouts $38,820.60 220305 February 9, 2022
Stella-Jones Corporation Poles $32,522.00 220320 February 15, 2022
Anixter Primary Cable 1100 $43,410.00 220338 February 22, 2022
RJB Wholesale Inc. Conduit 6" $44,054.40 220367 March 10, 2022
RJB Wholesale Inc. Conduit 3" $48,576.00 220395 March 23, 2022
Anixter Cable 4/0-2/0 Sweetbriar $49,000.00 220427 April 1, 2022
Anixter Cable 350-4/0 Wesleyan $58,200.00 220427 April 1, 2022
Anixter Primary Cable #2 $116,000.00 220426 April 1, 2022
NOJA Power LLC Reclosers $69,000.00 220444 April 8, 2022
General Pacific Inc. Sectionalizing Enclosure $38,358.00 220483 April 28, 2022
Stuart C Irby Co. Cable 350-4/0 Wesleyan $30,400.00 220482 April 28, 2022
RJB Wholesale Inc. Conduit 3" $56,848.00 220492 May 3, 2022
General Pacific Inc. Primary Cable #2 $66,520.00 220495 May 4, 2022
Elliott Industries Inc. Switching Enclosure $90,984.00 220525 May 16, 2022
RJB Wholesale Inc. Conduit 6" $89,640.20 220552 June 7, 2022
Oldcastle Infrastructure Oil Water Separator - Westport Sub $33,423.77 220592 June 30, 2022
Oldcastle Infrastructure Oil Water Separator - State St. Sub $33,423.77 220591 June 30, 2022
Oldcastle Infrastructure Oil Water Separator - Central Park Sub $33,423.77 220590 June 30, 2022
Stuart C Irby Co. Cutout $31,752.00 220603 July 1, 2022
Elliott Industries Inc. Switching Enclosure $43,786.00 220611 July 7, 2022
Stella-Jones Corporation Poles $36,405.00 220619 July 18, 2022
Anixter Primary Cable 4/0 $39,750.00 220633 July 21, 2022
General Pacific Inc. Primary Cable #2 $66,200.00 220634 July 21, 2022
Stuart C Irby Co. Conduit 3" $45,584.00 220644 August 1, 2022
Anixter Cable 4/0-2/0 Sweetbriar $49,000.00 220656 August 9, 2022
Anixter Triplex Wire #4 Non Pariel $63,300.00 220656 August 9, 2022
Anixter Switching Enclosure $40,249.90 220679 August 22, 2022
RJB Wholesale Inc. Conduit 6" $35,022.00 220733 September 23, 2022
General Pacific Inc. Wire 750 - 61 Strand $45,789.00 220750 October 5, 2022
Stella-Jones Corporation Poles $37,665.00 220773 October 18, 2022
Stella-Jones Corporation Poles $32,968.25 220832 November 23, 2022
Stella-Jones Corporation Poles $37,884.24 220830 November 23, 2022
Stella-Jones Corporation Poles $48,240.00 220831 November 23, 2022
Elliott Industries Inc. Switching Enclosure $87,886.00 220839 December 1, 2022
General Pacific Inc. 115 KV Insulators $52,965.00 220856 December 8, 2022
Columbia Electrical Supply Conduit 3" $51,534.91 220864 December 13, 2022
Anixter Cable 4/0-2/0 Sweetbriar $108,800.00 220873 December 15, 2022
Anixter Cable 350-4/0 Wesleyan $110,000.00 220873 December 15, 2022
General Pacific Inc. Wire 500 - 37 Strand $34,200.00 220870 December 15, 2022
General Pacific Inc. Primary Cable #2 $110,175.00 220870 December 15, 2022
Stella Jones Corporation Poles $44,867.24 220884 December 20, 2022

 

2021 Small Works Roster Project Awards
Contractor/Contractor Registration Number Description of Work Contract Amount PO # Date Contract Awarded Project Manager
Advanced Heating & Air

ADVANHA955OF

ADVANHA9556F

Routine & Emergency HVAC Services $59,862 21-0528 June 3, 2021 Brian Pickering
Advanced Heating & Air

ADVANHA955OF

ADVANHA9556F

New HVAC Unit – Highlands Substation $7,350 21-0685 September 8, 2021 Brian Pickering
Advanced Heating & Air

ADVANHA955OF

ADVANHA9556F

New HVAC Unit – System Control $12,976 21-0631 August 4, 2021 Brian Pickering
Asplundh Tree Expert

ASPLUTE833QA

Vegetation Management Mowing $165,000 21-0290 January 12, 2021 Todd Plato
Hugo’s Lawn Services

UBI # 603621957

Landscaping Services $45,740 21-0700 August 20, 2021 Brian Pickering
Lupo Construction

JOHNLCI099NL

Control Enclosure Roof Repairs – Elma and South Elma $18,390 21-0335 March 3, 2021 Vaughn Hamilton
Magnum Power

MAGNUPL962Q4

MAGNUPL96284

Directional Boring – Not to Exceed $50,000 $50,000 21-0782 October 22, 2021 Todd Plato
Magnum Power

MAGNUPL962Q4

MAGNUPL96284

Elma Gate Road Project $93,000 21-0830 August 13, 2021 Tyson Reeves
Magnum Power

MAGNUPL962Q4

MAGNUPL96284

Directional Boring – 60 Day Term $35,000 21-0687 September 8, 2021 Todd Plato
Rognlin’s

ROGNL**342LF

Credit Department Remodel Project $155,000 21-0562 July 6, 2021 Brian Pickering
Sunset Air

SUNSEAI915B1

SUNSEA*220CM

Routine and Emergency HVAC Services – Not to Exceed $50,000 $50,000 21-0330 February 25, 2021 Brian Pickering
2021 Small Work Project Awards
Contractor/Contractor Registration Number Description of Work Contract Amount PO # Date Contract Awarded Project Manager
Advanced Heating & Air

ADVANHA955OF

ADVANHA9556F

Routine & Emergency HVAC Services $59,862 21-0528 June 3, 2021 Brian Pickering
Advanced Heating & Air

ADVANHA955OF

ADVANHA9556F

New HVAC Unit – Highlands Substation $7,350 21-0685 September 8, 2021 Brian Pickering
Advanced Heating & Air

ADVANHA955OF

ADVANHA9556F

New HVAC Unit – System Control $12,976 21-0631 August 4, 2021 Brian Pickering
Asplundh Tree Expert

ASPLUTE833QA

Vegetation Management Mowing $165,000 21-0290 January 12, 2021 Todd Plato
Hugo’s Lawn Services

UBI # 603621957

Landscaping Services $45,740 21-0700 August 20, 2021 Brian Pickering
Lupo Construction

JOHNLCI099NL

Control Enclosure Roof Repairs – Elma and South Elma $18,390 21-0335 March 3, 2021 Vaughn Hamilton
Magnum Power

MAGNUPL962Q4

MAGNUPL96284

Directional Boring – Not to Exceed $50,000 $50,000 21-0782 October 22, 2021 Todd Plato
Magnum Power

MAGNUPL962Q4

MAGNUPL96284

Elma Gate Road Project $93,000 21-0830 August 13, 2021 Tyson Reeves
Magnum Power

MAGNUPL962Q4

MAGNUPL96284

Directional Boring – 60 Day Term $35,000 21-0687 September 8, 2021 Todd Plato
Rognlin’s

ROGNL**342LF

Credit Department Remodel Project $155,000 21-0562 July 6, 2021 Brian Pickering
Sunset Air

SUNSEAI915B1

SUNSEA*220CM

Routine and Emergency HVAC Services – Not to Exceed $50,000 $50,000 21-0330 February 25, 2021 Brian Pickering
2020 Small Works Project Awards
Contractor/Reg. Number Description of Work Contract Amount PO Number Date Contract Awarded Project Manager

Brumfield Construction

BRUMFCI114K4

Routine & Emergency Dirt Work $349,000 20-0311 February 21, 2020 Todd Plato

PNE Corp. d/b/a Cowlitz Clean Sweep

COWLICS971LO

Routine & Emergency Vac Truck Services $290,000 20-0280 February 5, 2020 Steve Easton
2019 Small Works Project Awards
Contractor/Reg. Number Description of Work Contract Amount PO Number Date Contract Awarded Project Manager
Asplundh Tree Expert, LLC Vegetation Management Mowing Services $200,000 18-0769 January 10, 2019 Todd Plato
Rognlin’s, Inc. Customer Service and Old Energy Services Department Remodel $17,650 19-0241 February 12, 2019 Brian Pickering
Star Electric Electrical Work – CCAP Comm Building $748.12 18-0778 January 16, 2019 Mark Forsman